The arrival of the first LNG carrier marked a historic moment for the LNG Canada project. This inaugural cargo initiated...
⚙️ A high-precision concrete slab
Designed to support the entire tank, the reinforced concrete slab is a key component of the containment system. Its construction required:
• Millimetric planarity to preserve the integrity of the LNG storage
• Phased execution adapted to the site’s complex harsh climatic conditions
• Strict quality control to meet the highest concrete standards
⚙️ A structural concrete wall with a critical dual function
Surrounding the slab, a 46-meter-high post-tensioned reinforced concrete wall (entirely in-house engineered) was progressively built. This massive structure ensures:
✅ Structural support for the dome during and after installation
✅ The containment barrier system imposed by codes and regulations
✅ Resistance to external hazard such as fire or blast,
✅ The post-tensioning works were carried out by Freyssinet, also part of VINCI Construction, whose advanced structural anchoring systems contributed to ensuring the long-term performance and durability of the infrastructure.
⚙️ A reinforced concrete roof (after erection of the steel cupola) to ensure :
✅ support for the top platform and tank accessories
✅ resistance to external hazard such as fire or blast,
Together, the slab, wall and roof form the safety monolithic envelope of a “full containment” tank, built in accordance with the world’s most stringent LNG storage standards.
🗓️ Seamless execution, mastered timelines
This pivotal phase mobilised multiple teams across quality, construction, and scheduling. It was delivered:
• On top of foundations built to millimetric tolerances
• With effective collaboration between trades, ensuring seamless coordination and execution
• Just ahead of the successful dome air-lifting operation
This civil engineering achievement demonstrates Entrepose Contracting’s ability to deliver technically demanding infrastructure that meets the highest standards in safety, sustainability, and performance.
📢 Next up: the spectacular air raising of a 1,540-tonne steel dome, spanning 92 meters. Stay tuned to discover how precision engineering meets innovation in the next stage of the LNG Canada journey
#LNGCanada #CryogenicTank #CivilEngineering #ConcreteSlab #ContainmentWall #EPC #EntreposeContracting #VINCIConstructionGrandsProjets #Kitimat #Foundations #EnergyTransition #EngineeringExcellence
LNG Canada Uzo Ojimadu, MBA, Jordan Keim Eric Priore @freyssinet

The client was expecting a physical scale model of its industrial facility to be delivered to its offices in time for Christmas.
Two months before the deadline, the model was damaged during customs processing. Repairing it in time was no longer possible. It was

One day, he helps the proposal teams put a price on a solution. The next day, he defines temporary installations and lifting plans or drafts an implementation procedure in collaboration with the engineering and construction teams. Every choice of method affects the timeline, costs… and