This page brings together the latest news from Entrepose Contracting and offers a glimpse into our day-to-day operations: major projects, technical expertise, significant developments and the key milestones that shape the life of the company. A space where you can follow our contribution to the energy infrastructure of today and tomorrow.

Featured news

26/05/2026

The arrival of the first LNG carrier marked a historic moment for the LNG Canada project. This inaugural cargo initiated the cool down sequence, allowing the Storage Tank to safely reach cryogenic conditions — a decisive step toward full operation.

01/04/2026

Before the cryogenic tank could enter service, a critical verification was successfully completed: the hydrostatic and pneumatic tests of the tank.

Latest News

26/05/2026

The arrival of the first LNG carrier marked a historic moment for the LNG Canada project. This inaugural cargo initiated the cool down sequence, allowing the Storage Tank to safely reach cryogenic conditions — a decisive step toward full operation.

28/04/2026

Following the acceptance of the hydrostatic and pneumatic tests, the LNG Canada project reached a key milestone: the closure of the tank and inerting with nitrogen.

01/04/2026

Before the cryogenic tank could enter service, a critical verification was successfully completed: the hydrostatic and pneumatic tests of the tank.

05/03/2026

Following the successful installation of the suspended deck, the LNG Canada project has reached another major breakthrough with the construction of the inner tank shell, the primary containment system for LNG storage.

04/02/2026

After installing the process modules, the LNG Canada project team undertook on a strategically timed phase: the cryogenic insulation of the suspended deck

08/01/2026

After lifting the 1,540 ton roof dome, the LNG Canada project reached another key logistical and technical milestone: the installation of the process modules designed to ensure safe, efficient, and continuous LNG storage and sending-out operations.

15/12/2025

Following the installation of the innovative foundation system for the main LNG Canada tank, executed by Soletanche Bachy Canada, expert in foundations and soil technologies and subsidiary of VINCI Construction, the teams at Entrepose Contracting and VINCI Construction Grands Projets began work on a full-containment, in-house engineered, civil concrete monolithic structure to meet the formidable challenges of the Kitimat site.