Customer :
Gate terminal BV
Role :
EPC Contractor
Key date :
September 2023 to December 2026
Location :
Maasvlakte, Rotterdam - Netherlands
Description of the Project
Gate terminal B.V. is expanding its LNG storage and regasification capacity with the construction of a fourth full‑containment LNG tank (24‑T‑01) at Maasvlakte, Rotterdam. This strategic investment strengthens energy security for the Netherlands and neighboring markets.
Client: Gate terminal B.V.
Contractor: ENVI JV (Entrepose Contracting + VINCI Construction Grands Projets)
Tank Capacity: 180,000 m³
Target Commissioning: Second half of 2026
Work done and added value of our solution
Design & Engineering: Full‑containment LNG tank with nickel‑steel inner tank and pre‑stressed concrete outer shell.
Procurement & Construction: Civil works, roof assembly, mechanical and E&I installation.
Pre‑Commissioning & Training: Hydrotests, functional checks, and readiness for cool‑down/start‑up.
Added values
- Energy Security & Market Impact
Increases LNG storage by 180,000 m³, boosting Gate Terminal’s regasification capacity by ~4 bcm/year.
Supports diversification of gas supply for the Netherlands and neighboring EU markets. - Proven Expertise
Delivered by ENVI JV (Entrepose + VINCI), leveraging experience from the first three Gate Terminal tanks.
Advanced engineering and construction methods ensure reliability and safety. - Sustainability & Compliance
Designed to meet highest safety and environmental standards for cryogenic LNG storage.
Incorporates efficient construction practices and optimized material use. - Digital Project Management
Full integration with EDMS/e‑Project workflows for document control and traceability.
Streamlined review cycles and MDR compliance for faster approvals. - Economic & Strategic Benefits
Strengthens Rotterdam’s position as a key European LNG hub.
Contributes to long‑term energy transition strategies by enabling flexible LNG imports.